In order to obtain the best pricing and product quality, a project manager should:
A. obtain an RFP from one vendor who can provide the products.
B. obtain an RFP from the vendor who provides the lowest priced products.
C. obtain responses from different vendors to compare the products.
D. use past vendors who have provided all project deliverables.
A project manager has failed to obtain the necessary permits from the local building commission. The project has been stopped because of a failure to understand the importance of:
A. internal process compliance.
B. risk avoidance.
C. standards compliance.
D. audit trail compliance.
A customer requests that the products quality be reduced to control its cost. Which of the following actions should the project manager take FIRST?
A. Modify the project schedule.
B. Obtain approval for the change.
C. Reduce the amount of project resources to control costs.
D. Modify the project budget.
Changing the project schedule to prevent a known risk is an example of which of the following risk responses?
A. Mitigation
B. Avoidance
C. Acceptance
D. Transference
Which of the following is true of a work breakdown structure (WBS)? (Select Two).
A. It consists of work packages at the top level which are decomposed to increasingly detailed levels.
B. It is a quantitative analysis tool used in quality management to analyze defects.
C. Each descending level represents an increasing detailed definition of the project work.
D. It is developed during the planning process and used to create the project scope statement.
E. It organizes and defines the total scope of the project.
Add Comments
Very good JK0-017 dumps, take full use of it, you will pass the exam just like me.
The content of this dumps is rich and complete, you can find that all the answers of questions from this dumps. Very useful.
There are so many new questions in the latest update. You can trust on this. Good luck to you all, guys.
i have passed today, All the questions are from their dumps, thanks for this dumps.
In the morning i received the good news that I have passed the exam with good marks. I'm so happy for that. Thanks for the help of this material.
Passed today......... Thanks a lot guys! I only Study your manuals and sims. Valid dumps! Good luck to u all~!
Absolutely valid. i passed today. You are the best. Thanks so much.
Passed my exam today. Great job.Thanks this dumps.
A valid dumps. It helped me pass the exam in short time. Thanks a million.
Thanks a lot and good luck to everybody.