PMI-SP Online Practice Questions and Answers

Questions 4

You are the project manager of the NHQ Project. Management has set a conformance to the project schedule for your project at 0.95. What does this term mean?

A. It means the largest schedule variance you can have is five percent.

B. It is the earned value divided by the planned value for your project.

C. It is the expectation of management to be 95 on schedule at 95 percent of the project.

D. It means you will need to earn at least 95 cents per dollar invested in the project.

Browse 323 Q&As
Questions 5

John works as the project manager for Honeywell Inc. He is involved in the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress. Which of the following techniques is used in generating performance reports?

A. Work performance information

B. Change requests

C. Work performance measurements

D. Forecasting method

Browse 323 Q&As
Questions 6

You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?

A. -$135,000

B. .67

C. .81

D. -$65,000

Browse 323 Q&As
Questions 7

Which of the following statements best describes an activity in a project?

A. It is a defined set of functions a resource must complete for the project scope to be considered complete.

B. It is the effort needed to complete a work package.

C. It is the unit of resource utilization needed to complete a project deliverable.

D. It is a listing of all project work that must be accomplished for the project scope to be considered complete.

Browse 323 Q&As
Questions 8

You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what is your schedule performance index. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450, what is the SPI for this project?

A. $227,140

B. 0.75

C. 0.95

D. -$56,789

Browse 323 Q&As
Questions 9

You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below: MeasurementsValues BCWP (or EV)325 BCWS (or PV) 300 ACWP (or AC)410 What is the schedule variance (SV) of the project at the current point of time?

A. +110

B. -25

C. -110

D. +25

Browse 323 Q&As
Questions 10

You are the project manager of the GHQ Project. You have to prioritize activities for the effective management of project. For this, you have created a network diagram to schedule a set of project activities as shown in the figure:

Based on this figure, what is the critical path of this project?

A. ABEHJ

B. ACFIJ

C. ADGJ

D. ACFGJ

Browse 323 Q&As
Questions 11

You are the project manager of the OOI Project and you're forty percent complete with this project. The project has a BAC of $2,345,650 and you have spent $950,000 to date. Based on your aggressive scheduling you should be at the 45 percent milestone today, but due to some early delays you're running late. What is the planned value of your project?

A. $950,000

B. $2,375,000

C. $1,055,543

D. $938,260

Browse 323 Q&As
Questions 12

Mary is the project manager for her organization. She is working with the project team to define the project activities. She is concerned about some of the dependencies of the project work, which may affect the project schedule. Which one of the following is the best example of a project constraint that will likely affect the project's ability to finish by a given deadline?

A. The project must use internal team members to complete the project work.

B. The project must adhere to several regulations.

C. The project must use the BGH company to deliver the software portion of the project.

D. The project must not exceed $1,250,000.

Browse 323 Q&As
Questions 13

You are the project manager of the NHQ Project. You are coaching Alice, a new project manager, on the relationships in a project network diagram. Which relationship type between activities are the most common?

A. SS

B. FS

C. FF

D. SF

Browse 323 Q&As
Questions 14

Robert is the project manager for his organization. Management has asked Robert to provide them with the metric he uses to measure deliverables status, costs incurred, and especially how he measures the schedule progress for schedule adherence. What project component could Robert provide for management?

A. Milestone list

B. Cost management and the project schedule

C. Work performance measurements

D. Project management plan

Browse 323 Q&As
Questions 15

A project manager is reviewing her project performance. Her project has a BAC of $950,000 and is currently 40 percent complete, though it was scheduled to be 45 percent complete at this time. Her project has spent $387,526. Management would like to know if there is a schedule variance. What is the planned value for this project?

A. -$47,500

B. 0.89

C. $427,500

D. 0.98

Browse 323 Q&As
Questions 16

You are the project manager of the NHQ project. This project is currently running about 15 percent behind schedule and the management has asked you to rectify the problem. You have elected to crash the project. What does this term mean?

A. Reject all proposed change requests for the project.

B. Add resources to the project work.

C. Add cost to the project budget.

D. Cut non-value added activities to the project.

Browse 323 Q&As
Questions 17

You work as a stakeholder for ABC Inc. You are on an important feature of a project that appears too difficult to execute. Issues like acceptable type of bugs and number of bugs for user acceptance seem to have affected the project. What is the rate of risk factor in such a situation?

A. Risk factors are rated high.

B. Risk factors are rated low.

C. Risk factors are rated medium-high.

D. Risk factors are rated medium.

Browse 323 Q&As
Questions 18

You are the project manager of the NHQ project. This project is scheduled to last for six months and will require $345,000 to complete. If the project completes earlier than scheduled, your organization will receive a bonus of $5,000 per day for the early completion. Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible, but you must be careful not to increase project risk beyond an acceptable level of risk exposure. Which of the following approaches is most likely to increase project risk?

A. Using the critical chain method

B. Crashing

C. Adding leads to the project work

D. Fast tracking

Browse 323 Q&As
Exam Code: PMI-SP
Exam Name: PMI Scheduling Professional
Last Update: Apr 21, 2024
Questions: 323 Q&As