A company produces generic and name-brand paper plates in the same factory using standard costing and using the same Bill of materials and routes to produce both products.

The finance and production teams want a way to view individual raw material consumption costs in the ledger.

You need to add a production group to control postings to the ledger.

What should you do?

A. Create a production group for the finished good item

B. Update the cost of the generic finished good item

C. Create a production pool for the finished good item

D. Create a new Bill of materials with alternate costs for the raw material

Browse 230 Q&As
Questions 5

You are the production supervisor in charge of setting effective cost prices for the labor force in a manufacturing company.

It is the end of the year and the labor rates have been recalculated based on new salary data.

You need to update the effective labor costs for all labor groups.

Which element must be updated?

A. cost groups

B. shared category

C. resource group

D. cost category

E. production orders

Browse 230 Q&As
Questions 6

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while

others might not have a correct solution.

After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.

A company uses Dynamics 365 Supply Chain Management to manage production configuration.

A product designer creates a remote control toy that can be purchased with different tire sizes.

Sales representatives need to perform product configuration for the custom tire variants when they create a new order.

Solution: Select the custom tire size when filling out each sales order line.

Does the solution meet the goal?

A. Yes

B. No

Browse 230 Q&As
Questions 7

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some questions sets might have more than one correct solution,

while others might not have a correct solution.

After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.

A company implements Dynamics 365 Supply Chain Management for their Lean manufacturing environment.

There has been an engineering change to a fixed quantity product that is in production. This change will add an additional processing step as the second step. The existing version must be phased out and replaced by the new version.

You need to ensure that the engineering change takes affect at the end of the month.

Solution:

1.

Edit the existing production flow and set the expiration date to the end of the month.

2.

Using the existing production flow, create a production flow and version. Set the expiration date to the end of the month. Create an activity for the new process step and add it in the proper sequence.

3.

Create a Kanban rule that uses the last day of the month as the effective date.

4.

Edit the existing Kanban rule. Set the expiration date to the end of the month. Set the new Kanban rule as the replacement Kanban rule.

5.

Activate the new production flow. Does the solution meet the goal?

A. Yes

B. No

Browse 230 Q&As
Questions 8

A company implements Dynamics 365 Supply Chain Management.

Due to increased demand and limited space in the work cell area for product L0050, you must subcontract overflow work to another company. You have the following requirements:

1.

Locate a warehouse at the subcontractor building.

2.

Support picking and shipping activity tracking.

3.

Associate costs of transporting materials between the locations in the cost of the finished product. You need to modify the production flow.

Which three actions should you perform? Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.

A. Modify the overflow work activity and assign it to subcontractor

B. Create transfer activities and assign them to the subcontractor

C. Create a resource and work cell resource group for the subcontractor

D. Create a new production flow version

E. Modify the overflow work operation and associate it with the subcontractor

Browse 230 Q&As
Questions 9

You have a product that can be manufactured on two different production lines in the same warehouse. You create resources and then create individual input locations for the resources. You create two routes.

Each route uses different resources.

Materials are staged for consumption in different locations based on the resources being utilized for production.

You need to set up the formula to consume the goods from the correct line-side location.

What should you do?

A. Select a warehouse and consumption operation for each line.

B. Select resource consumption and the operation for each line.

C. Select the plan group and consumption operation for each line.

D. Specify a site in the formula header.

Browse 230 Q&As
Questions 10

You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item. The item has the following Lean setup:

1.

The setup uses a Lean schedule group with a throughput ratio=2

2.

The process activity tied to production flow has the following runtime activity times: time=3 min, per quantity=1

3.

The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8-hour day)

4.

The throughput is 10 per hour

You need to set up a Discrete operation to mirror the item's production flow activity.

What should you do?

A. Create a route with a runtime =1, a process quantity =6, and the operation's hours/time =1

B. Create a route with a runtime =1, a process quantity =10, and the operation's hours/time =1

C. Create a route with a runtime =6, a process quantity =1, and the operation's hours/time =1

D. Create a route with a runtime =10, a process quantity =6, and the operation's hours/time =1

Browse 230 Q&As
Questions 11

A company plans to use master planning in Dynamics 365 Supply Cha-n Management. The company will sell items between legal entities.

The company has several facilities across legal entities that can manufacture the same products- Some products are produced only in some plants. To meet product demand, when one facility rs over capacity, another facility is used to fulfill the downstream demand.

The organizational entities are: Legal Entity A: Plant 1,2, and 3 Legal Entity B: Plant 4 and S Legal Entity C: Plant 6. 7. and 8

The following plants must be planned together Plan1, Plant 3, and Plant 4 Plant 2, Plant 6, and Plant 8 Plant 5 and Plant 7

You need to configure master planning for the facilities. Which configuration mechanism should you use?

A. Intercompany planning groups

B. Coverage groups

C. Item model groups

D. Production groups

Browse 230 Q&As
Questions 12

A company uses Lean manufacturing processes with Kanban boards.

When unexpected transfer jobs occur, the board do not clear properly.

You need to ensure that the boards clear properly.

What are two possible ways to clear the board? Each correct answer presents a complete solution.

NOTE: Each correct selection is worth one point.

A. Change unplanned to planned.

B. Delete the unplanned job.

C. Revert the planned Kanban job status.

D. Remove the planned Kanban job.

Browse 230 Q&As
Questions 13

You need to track the cost of donating leftover flour and sugar to local food banks. Which production option should you configure?

A. by-product

B. scrap percentage

C. batch attribute

D. catch weight

Browse 230 Q&As
Questions 14

SIMULATION

You are a functional consultant for Contoso Entertainment System USA (USMF).

You need to configure the system to ensure that planned master orders generated by Material Requirements Planning (MRP) contain trade agreements.

To complete this task, sign in to Dynamics 365 portal.

Browse 230 Q&As
Questions 15

A skateboard manufacturer uses route operations to schedule resources and estimate units per hour. All products use the sample sub assembly item and resource sanding process.

You observe an increase in the number of units a sanding belt resource can produce. The production schedule is now inaccurate due to the number of units the sanding belt line can produce.

You must make a permanent change to the number of units the resource can produce for all future orders.

You need to adjust the process quantity on the route operation.

Which three actions should you perform in sequence? To answer, move the appropriate actions form the list of actions to the answer area and arrange them in the correct order.

Select and Place:

Browse 230 Q&As
Questions 16

A configure-to-order company is implementing Dynamics 365 for Finance and Operations. The company is preparing to use the product configuration model functionality to develop the Bill of materials (BOM), routes and valid configuration

combinations.

You need to set up the configuration models, constraints, and pricing.

In which order should you perform the actions? To answer, move all actions from the list of actions to the answer area and arrange them in the correct order.

Select and Place:

Browse 230 Q&As
Questions 17

A process manufacturing company is implementing rebates in Dynamics 365 for Finance and Operations for some of their customers on specific items.

You are the production consultant in charge of implementing the processes needed for calculating and applying the rebates for the subset of customers and items.

You need to implement the order of transactions to process the rebates.

In which order should the actions be performed? To answer, move all actions from the list of actions to the answer area and arrange them in the correct order.

Select and Place:

Browse 230 Q&As
Questions 18

HOTSPOT

A company uses Dynamics 365 Supply Chain Management.

The company plans to use the Asset management module to maintain its installed base of milling machine fixtures.

The module must be configured to handle the following requirements:

An oil sampling must be taken from each machine at regular intervals.

All calibration types (tooling, instrumentation, and tolerances) that share a required performance skillset must be managed together.

The company is unable to perform in-house preventive maintenance skills on the pneumatic tapping machines. Therefore, the company hires outside services for it.

All maintenance must be scheduled at the same time for efficiency and cost savings.

You need to configure the system.

Which option should you configure? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.

Hot Area:

Browse 230 Q&As
Exam Code: MB-320
Exam Name: Microsoft Dynamics 365 Supply Chain Management, Manufacturing
Last Update: Aug 27, 2023
Questions: 230 Q&As

PDF

$45.99

VCE

$49.99

PDF + VCE

$59.99