You are a Project Manager in your organization who is managing a considerably huge budget project to develop new software. Considering the varied nature of your stakeholder group, you would like to put together a plan as to what information the stakeholders need, and how to provide that information. What is the document that you would need, and as part of which process group would you achieve this?
A. Communications Management Plan, Execution Process group
B. Project Management Plan, Planning Process Group
C. Communications Management Plan, Planning Process Group
D. Project Management Plan, Initiating Process Group
You are a new Project Manager who has been entrusted with a project. You have been directing and managing the execution of your project. Which of the following is the most likely outcome as part of this phase of the project?
A. Expert Judgment
B. Lessons learned
C. Project Charter
D. Approved Deliverables
You are the project manager for the NHQ Project. Your project has 76 stakeholders. Two of your key stakeholders, Nancy Smith, the COO, and Chuck Thomas, the CIO, need to contribute information to one another and to you, the project manager, in order for the project to move forward. It comes to your attention that Chuck and Nancy are in disagreement with one another and won't communicate. This disruption has caused your project to come to a standstill. What component of the communication model does this scenario represent?
A. Feedback
B. Barrier
C. Medium
D. Noise
Which of the following conflict resolution techniques can bring the problem into the open and have the third person present?
A. Compromise
B. Collaboration
C. Avoidance
D. Accommodation
Which of the following process groups starts after the planning phase of a project is over?
A. Monitoring and Controlling
B. Initiation
C. Testing
D. Execution
Add Comments
Valid dumps. I hope all my friend will pass the exam, so I will introduce this dumps to them.Good luck to them and you.
This file is so much valid, I passed the GCPM exam successfully. thanks for my friend introduce this dumps to me.
I really felt surprised that i would pass the exam with so high score by using this dumps. I will share this good study material with my friends.
Absolutely valid. i passed today. You are the best. Thanks so much.
There are so many new questions in the latest update. You can trust on this. Good luck to you all, guys.
Great dumps! I have passed the exam by using this dumps only half a month. I will share with my friend.
Hello, guys. i have passed the exam successfully in the morning,thanks you very much.
So happy. I passed the exam with the help of this material. Good luck to you.
The version is complete and accurate. The most important is that this dumps update quickly and there are many new questions . So I felt confident in exam. Recommend.
The answers are accurate. Well you should notice some of the questions are slightly changed. Be careful.