What information does the project team need before they can.

A. Definition of done

B. Available project resources

C. Overall project schedule

D. Test strategy

Browse 86 Q&As
Questions 5

Which of the following are levels in the structure of an SAP Best practices solution package?

There are 2 correct answers to this question

A. Building blocks

B. Configuration guides

C. Scope items

D. Business process scenarios

Browse 86 Q&As
Questions 6

What are two important approaches, based on the control centre concept, that SAP Proposes to use for streamlined implementation and operations?

There are 2 correct answers to this question

A. Build SAP like a factory

B. Intelligent enterprise

C. Run SAP like a factory

D. Always connected

Browse 86 Q&As
Questions 7

In the "new implementation of SAP S/4HANA" transition path, which systems are part of the project system landscape? There are 2 correct answers to this question.

A. P-system

B. Starter system

C. DQAS

D. DEV

Browse 86 Q&As
Questions 8

Which artifacts are created within application design and configuration workstream in the explore Phase of the "New implementation of SAP S/4HANA"

There are 3 correct answers to this question

A. Project procedure-mock-up modeling

B. Roles and authorizations management concept

C. Delta requirements list-register

D. Detailed design-business process

E. Organisation structure specification

Browse 86 Q&As
Questions 9

Where can you find Data Migration templates?

A. SAP roadmap viewer

B. SAP S/4HANA Migration cockpit

C. SAP best practices explorer

D. SAP cloud appliance library

Browse 86 Q&As
Questions 10

How often will an upgrade be performed on an SAP S/4HANA cloud single tenant edition environment?

A. Schedule is defined by service level agreement for SAP HANA enterprise cloud and SAP S/4HANA Cloud single tenant edition services.

B. One upgrade and two feature packs per year

C. Every quarter

D. Every year

Browse 86 Q&As
Questions 11

Which estimation technique can be used in agile delivery approach to size the user Stories during sprint planning?

A. Detailed bottom-up effort estimate by the scrum master in story points based on the User story complexity

B. Product owners relative estimate of the effort that will be needed to implement the user story

C. Detailed bottom-up effort estimate that breaks each user story up into hours or shorter tasks

D. Relative estimate in ideal person days that reflects the best estimate provided By the project team

Browse 86 Q&As
Questions 12

Which of the following content best outlines the sequence of testing within the application Design and configuration workstream in the realize phase?

A. string test Integration test User acceptance test string test

B. User acceptance test Integration test integration test

C. User acceptance test String test data migration

D. String test User acceptance test

Browse 86 Q&As
Questions 13

How do you achieve frequent checkpoints with the end user in an Agile delivery approach?

There are 2 correct answers to this question.

A. Solution review for waves

B. Solution demo for sprints

C. User acceptance test

D. Demo the SAP model company

Browse 86 Q&As
Questions 14

Which of the following tools are specific to the Data Management work stream?

Note: There are 3 correct answers to this question

A. SAP Landscape Transformation

B. SAP Data Services

C. SAP S/4HANA Migration Cockpit (for both SAP S/4HANA Cloud and SAP S/4HANA editions)

D. SAP Roadmap Viewer

E. SAP Solution Manager

Browse 86 Q&As
Questions 15

How does the provisioning of SAP S/4HANA cloud differ from the setup of SAP S/4HANA?

Note: There are 2 correct answers to this question

A. There is a Preset phase for Q-system. which is unique for SAP S/4HANA Cloud.

B. SAP S/4HANA systems take less time to provision than SAP S/4HANA Cloud systems.

C. In SAP S/4HANA Cloud, decommissioning/shutdown of the Starter system is initiated automatically after the P-system is requested through the Manage Your Solution app, whereas in an SAP S/4HANA system, the DEV system persists.

D. To start a Solution Validation workshop, a DEV system is available for SAP S/4HANA, while a Starter system is required for Fit-to-standard for SAP S/4HANA Cloud.

Browse 86 Q&As
Questions 16

Which Value Chains does SAP Solution Manager 7.2 deliver? Note:There are 3 correct answers to this question.

A. Request-to-Fulfill

B. Requirements-to-Deploy

C. Cash-to-Order

D. Hire-to-Retire

E. Detect-to-Correct

Browse 86 Q&As
Questions 17

Which end-to-end turn-key application lifecycle management (ALM) solution can support You in managing requirements and software development for large Agile project

A. Change request management

B. Requirement management

C. Focused build

D. Solution manager test suite

Browse 86 Q&As
Questions 18

Via which media does SAP provide ready-to-run systems for SAP S/4HANA deployment? There are 2 correct answers to this question

A. Blu -ray disks

B. SAP App centre

C. SAP Solution Builder tool

D. SAP cloud appliance library

Browse 86 Q&As
Exam Code: C_ACTIVATE13
Exam Name: SAP Certified Associate - SAP Activate Project Manager
Last Update: Apr 21, 2024
Questions: 86 Q&As

PDF

$45.99

VCE

$49.99

PDF + VCE

$59.99