Certbus > IFPUG > IFPUG Certifications > I40-420 > I40-420 Online Practice Questions and Answers

I40-420 Online Practice Questions and Answers

Questions 4

ALERT SYSTEM - ALERT NOTIFICATION

Select the complexity of each function:

Hot Area:

Hot Area:

Browse 249 Q&As
Questions 5

The Human Resources (HR) application includes functionality to maintain the Department logical file.

Determine the complexity for department transactions. Select the complexity for each function.

Hot Area:

Hot Area:

Browse 249 Q&As
Questions 6

A Corporate Finance application is being developed.

The application adds or updates the Receivable logical file and the Payable logical file. The user requires that this information is sent to the Accounts application to keep accounting records consistent. The combined receivable and payable data is sent to the Accounts application daily at 8:00 PM. When implementing a solution to send the receivable and payable information, it was decided to include a header and trailer record with the accounts information. These records are used by the Corporate Finance user to ensure that

everything was technically correct when transmitting the file.

From the Names of Possible Functions listed identify the transactional functions for the Corporate Finance application. Select N/A if a Name of Possible Function does not apply.

Identify the functions used:

Hot Area:

Hot Area:

Browse 249 Q&As
Questions 7

Several functions are outlined within the following scenario for the Accounts Receivable application:

From the Names of Possible Functions listed identify the transactional functions for the Accounts Receivable application. Select N/A if a Name of Possible Function does not apply.

Identify the functions used:

Hot Area:

Hot Area:

Browse 249 Q&As
Questions 8

The Procurement application user requires the ability to control how and when reports are printed. The following list shows the specific user requirements for generating reports: From the Names of Possible Functions listed identify the transactional functions for the Procurement application. Select N/A if a Name of Possible Function does not apply. Identify the functions used:

Hot Area:

Hot Area:

Browse 249 Q&As
Questions 9

Which of the following is NOT an example of the purpose of a function point count?

A. To enable comparison of functionality delivered by two applications

B. To determine maintenance support cost per function point

C. To understand the percentage of lines of code that is being reused across three different applications

D. To determine the effort and duration of a development project

Browse 249 Q&As
Questions 10

The TDI is:

A. computed using the VAF

B. a value ranging between 0 and 5

C. the sum of the degree of influence

D. /-35%

Browse 249 Q&As
Questions 11

Which is the primary difference between an 1LF and an EIF?

A. An EIF is referenced by the application being counted, while an 1LF is not referenced

B. An EIF is referenced by the application being counted, while an ILF is maintained and not referenced

C. An ILF is not maintained by the application being counted, while an EIF is

D. An EIF is not maintained by the application being counted, while an ILF is

Browse 249 Q&As
Questions 12

Which transactional function cannot alter the behavior of the application?

A. EI

B. EO

C. EQ

D. Both A and C

Browse 249 Q&As
Questions 13

In an enhancement project an EI is counted as changed because an additional attribute is sent across the boundary. Before the enhancement the EI referenced 2 FTRs and 15 attributes crossed the boundary. How many FPs are measured for the enhancement project?

A. 4 FP

B. 6 FP

C. 3 FP

D. 7 FP

Browse 249 Q&As
Questions 14

An application originally valued at 327 FP was enhanced. The enhancement added 3 low EQs, 2 low EIs, 2 high EOs, and changed 3 low ILFs. What is the enhancement project functional size?

A. 29

B. 50

C. 356

D. 377

Browse 249 Q&As
Questions 15

The team has been asked to size the software associated with porting the Order Management system from one operating system to a different operating system. The project includes a one-time data conversion activity. Which of the following is true?

A. FP approach can be used to size both the operating system upgrade and the data conversion activity

B. FP approach can be used to size the operating system upgrade. The data conversion activity cannot be sized using FP approach

C. FP approach can be used for sizing the data conversion activity. FP approach is not suitable for sizing the operating system upgrade

D. FP approach cannot be applied to size either the operating system upgrade or the one-time data conversion activity

Browse 249 Q&As
Questions 16

The Order Entry Modification screen populates all order details into the Order logical file. The modification process also populates the Advance Shipment Notification logical file and references the Available Inventory logical file. The user required before and after images to be captured for 3 attributes in the Oder logical file. The technical team has decided to store this data in the Order Audit file for ease of access. How many transactional functions and logical files are counted in the modification process?

A. 2 EI and 4 FTRs for each EI

B. 1 EI and 4 FTRs for the EI

C. 1 El and 3 FTRs for the EI

D. 2 EI and 3 FTRs for each EI

Browse 249 Q&As
Questions 17

Which statement applies when counting FTRs for an EO?

A. Count one FTR for each base functional component that is maintained by the EO

B. Count one FTR for each unique data function that is accessed by the EO

C. Count one FTR for each unique base functional component that is accessed by the EO

D. Count one FTR for each data function that is written to by the EO

Browse 249 Q&As
Questions 18

For the scenario listed above calculate the aDFP using a VAF of 1.2.

A. 61.60

B. 73.26

C. 58.26

D. 69.60

Browse 249 Q&As