In the, Out Of The Box, Project Dashboard, the color code for tasks is:
A. Yellow to indicate a task is late
B. Red to indicate a task is due within one day
C. Green to indicate a task is not started
D. Orange to indicate a task is at risk
In the dashboard Image below, what is the red square indicatng?
A. The task is Complete
B. The task is not complete but not late or at risk
C. The task is a Milestone and is pending
D. The task is late
What is a critcal path for a project?
A. It is the sequence of tasks, beginning to end, that takes the longest
B. It is the sequence of tasks that has the most milestones
C. It is the path that has the most phase gates
D. It is the path that takes the shortest sequence tme
How many Budgets can be created per project?
A. 1
B. 2
C. 4
D. Unlimited
When you copy a Project, which of the following items are automatcally copied?
A. Approvals
B. Assignees
C. Routes
D. Tasks
What are the states of a Risk for the Out Of The Box applicaton?
A. Create, Actve, Complete
B. Create, Assign, Actve, Review, Complete
C. Create, Actve, Archive
D. Actve, Inactve
Int the following image, what does the dependency (FS) specify?
A. Import the points WBS task must fnish before the Filter the points task can start
B. Import the points WBS task must start before the Filter the points task can fnish
C. Import the points WBS task must fnish before the Filter the points task can fnish
D. Import the points WBS task must start before the Filter the points task can start
A hierarchy of tasks and subtasks is called what?
A. Gate
B. Milestone
C. Phase
D. Work Breakdown Structure