You are a Project Manager whose projects are integrated with Financial Management System (FMS). TheFMS pushes Actual Costs and Actual Hours to your projects as of the Actual Date.UpdatingPercent complete using the pushed Actual Dates,Actual Costs, and Actual Hours has createdinaccuratepicturesofthe overall%complete, because there are steps withinactivities that clearly have not completed.

Which PercentComplete Typewould be the best selection for activities in this project?

A. Physical

B. Units

C. Effort

D. Duration

Browse 70 Q&As
Questions 5

An activity is to be completed within a fixed time period and thetotalamount of work is fixed.

What duration type should be used?

A. Fixed Units

B. Fixed Duration and Units/Time

C. FixedUnits/Time

D. Fixed Duration and Units

Browse 70 Q&As
Questions 6

Select the true statement regarding the ability to create projects.

A. Any Responsible Manager can create a project.

B. Any user can create a project

C. Any Project Manager can create a project.

D. Any Admin Super user can create a project.

Browse 70 Q&As
Questions 7

Select two true statements about the Portfolio Analysis tab in Primavera P6 EPPM.

A. Conduct a side-by-side comparison of an unlimited number of portfolios.

B. Conduct a side-by-side comparison of two projects.

C. Conduct a side-by-side comparison of two portfolios.

D. Conduct a side by side comparison of the same project displayed in different view.

E. Conduct a side-by-side comparison of the same portfolio displayed in different view.

Browse 70 Q&As
Questions 8

When is"Store Period Performance" usually performed?

A. aftereachpay period

B. after the schedule isupdated

C. after Job Servicesvalidation

D. after working hours to enhanceperformance

Browse 70 Q&As
Questions 9

The Total Spending Plan Tally for a project is the sum of the Spending Plans assigned to .

A. each project in the Enterprise Project Structure (EPS)

B. each Work Breakdown Structure (WBS) element in the project

C. each immediate child Work Breakdown Structure (WBS) element

D. each immediate parent Work Breakdown Structure (WBS) element

Browse 70 Q&As
Questions 10

You received an email from a Portfolio Manager asking you to checkperformance metrics for the past months on each of the projects filtered for that portfolio.You cannot locate the portfolio that the email referenced.

What is probably the reason you cannot find the portfolio?

A. It Is a User Portfolio created by the Portfolio Manager

B. It is a User Filtered Portfolio that hasn't been refreshed.

C. You don't have the appropriate license for the Web.

D. You haven't been assigned as a resource to the projects.

Browse 70 Q&As
Questions 11

Identify the best definition of Funding Source.

A. Contributing source of funds for a project's financing are assigned in Project Details

B. Percentage of the total fund allocated to the project are created and managed at the Project level

C. Agency where funds will be allocated for the project

D. Removes unwanted portlets from the User Interface View

Browse 70 Q&As
Questions 12

Select the true statement regarding currencies.

A. Only one base currency is supported per database.

B. Currencies are updated dally as pet exchange rates.

C. Only 10 currencies are supported in Primavera.

D. Only two currencies are supported in Primavera.

Browse 70 Q&As
Questions 13

Select the statement that best describes "Manage Scenarios" functionality.

A. You can create a portfolio for your own use or for sharing with other users.

B. You can view portfolio data in different forms.

C. You can capture a snapshot of project data at a specific moment in time.

D. You can select a portfolio to work with or execute commands in the Action bar.

Browse 70 Q&As
Questions 14

Select the appropriate example that demonstrates how materials are measured inP6.

A. $75/minute

B. $75/Hour

C. $75/linear foot

D. $75/day

Browse 70 Q&As
Questions 15

You are working in aproject plan that has been baselinedmultiple times. Each of thebaslined reflectsexpected effort for three different sets of defined scope. After reviewing the plan, management has decided that a previous baseline/scope definition will be used going forward.

Which action should be executed in the Client?

A. Restore

B. Copy/Paste

C. Export

D. Check Out

Browse 70 Q&As
Questions 16

Issue Codes .

A. can be viewed by all users at all times

B. can have values assigned to them

C. are created in the Risks menu

D. cannot be edited after launch

Browse 70 Q&As
Questions 17

In your project, cost and work effort is not subject to change.

Which duration type should beused?

A. Fixed Units

B. Fixed Duration and Units/Time

C. Fixed Units/Time

D. Fixed Duration and Units

Browse 70 Q&As
Questions 18

Identify three best practice uses of Notebook topics.

A. Document processes.

B. Explain a Constraint.

C. Send out an email alert.

D. Explain baseline update.

E. Change User Access.

F. Update Actual Costs.

G. Provide additional status information

Browse 70 Q&As
Exam Code: 1Z0-535
Exam Name: Primavera P6 Enterprise Project Portfolio Management Essentials
Last Update: Apr 21, 2024
Questions: 70 Q&As

PDF

$45.99

VCE

$49.99

PDF + VCE

$59.99