Vendor: PMI
Certifications: PMI Certification
Exam Name: PMI Risk Management Professional
Exam Code: PMI-RMP
Total Questions: 580 Q&As ( View Details)
Last Updated: Apr 13, 2024
Note: Product instant download. Please sign in and click My account to download your product.
VCE
PMI PMI-RMP Last Month Results
PMI-RMP Q&A's Detail
Exam Code: | PMI-RMP |
Total Questions: | 580 |
Single & Multiple Choice | 577 |
Fill in the Blanks | 3 |
CertBus Has the Latest PMI-RMP Exam Dumps in Both PDF and VCE Format
PMI-RMP Online Practice Questions and Answers
Which one of the following is the only output for the qualitative risk analysis process?
A. Enterprise environmental factors
B. Project management plan
C. Risk register updates
D. Organizational process assets
As a part of monitoring and controlling the project, the project manager should update the risk register. The project manager should update the risk register with information on risk reassessment, risk audits, and periodic risk reviews. What other information should the project manager update the risk register with?
A. Actual costs and schedule delays of risk events.
B. Actual outcomes of risk management duties by the project team.
C. Actual cost of risk events.
D. Actual outcomes of the project's risks and of the risk responses.
Linda is the project manager of the NAB Project. One of the risks her project team has identified is too dangerous for the project team to manage internally so she has hired a vendor to complete this portion of the project and to manage the identified risk. What risk response has Linda used in this instance?
A. Transference
B. Avoidance
C. Contractual
D. Mitigation
Don has hired Jerry, a contractor, to complete a portion of his project work. The contract used was a cost-plus contract. If Don were to perform a risk audit, who would carry the risk in this scenario?
A. Don would because he is the project manager.
B. Jerry would because of the contract type.
C. Don would because of the contract type.
D. Jerry would because he is the hired contractor.
Which of the following success factors will enhance the Perform Qualitative Risk Analysis process as the risk occurrence gets closer?
A. Agreed-upon definition
B. Iterative analysis
C. High quality information
D. Agreed-upon approach
Add Comments
thanks god and thank you all. 100% valid. you can trust on it.
The new questions in the exam are not the new questions for me because I have met them when I used this material . So there is no doubt that I have passed the exam with high score. Recommend this material strongly.
I'm very happy that I have passed the PMI-RMP exam with high score. I will share this good dumps with my friend. You can trust on it.
This dumps is valid, and this dumps is the only study material i used for this exam. Surprisingly i met the same question in the exam, so i passed the exam without doubt. Thanks for this dumps and i will recommend it to my friends.
update quickly and be rich in content, great dumps.
Recommend this PMI-RMP exam dump to you strongly, really useful and convenient.
There are so many new questions in the latest update. You can trust on this. Good luck to you all, guys.
There are many new questions in the dumps and the answers are accurate and correct. I finished my exam with high score this morning, thanks very much.
Passed full scored. I should let you know. The PMI-RMP exam dump is very good, valid and accurate.